Thru-Bolt
Split Ring Tube Alignment Castings
The patented "Thru-Bolt"
system developed by Power & Industrial Services for split
ring tube alignment castings can be installed by a single
person in far less time than required by standard procedures
requiring two people.
Eliminate
and Save
NO...fixture or
power jacks needed for tube alignment.
NO...helper needed to hold split ring tubes together during
welding.
|
Materials
Chart
|
|
*SFSA
|
ASTM
|
ASTI
|
|
HH
|
A297
|
309
|
|
HK
|
A297
|
310
|
|
Inconel
|
A297
|
-
|
|
50/50
Cb
|
A560
|
-
|
|
ST**
|
2300°
- 2450°
|
*Steel Founders
Society of America
**Cobalt based alloy
|

- Using one section
of the "Thru-Bolt" casting, insert the stainless
steel bolts into the special recesses located on the side
and weld over the heads.
- Position the
required number of tubes, then slide the second half of
the casting onto the installed bolts.
- Use the special
deep socket to tighten the stainless nut provided until
both halves of the casting have properly aligned the tubes.
- Weld the nuts,
thru pins, and ends, if possible, to complete installation.
|